Bidder Selection Plan

Phase 2 contractor selection plan Project: Installing additional 110kV horizontal capacitors on the Northern transmission grid year 2026

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 21:03 07/01/2026
Contractor Selection Plan ID
PL2600003378-00
Publishing time
21:02 07/01/2026
Posting Status
Published
Contractor selection plan name
Phase 2 contractor selection plan Project: Installing additional 110kV horizontal capacitors on the Northern transmission grid year 2026
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Spending Category
Investment and Development Spending
Authority that issues the decision
EVNNPT
Approval date
07/01/2026
Approval ID
20/QĐ-EVNNPT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 6
1.Package 3: Supply and transport the most VTTB
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
International
Bidding method
Directly
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and transport the most VTTB
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.Tender package No 4.1: Supply and transportation of secondary VTTB and configuration of KMT power system at transformer stations: West Hanoi 500kV substation, Hiep Hoa 500kV substation, Truc Ninh 220kV substation, Phu Binh 220kV substation, Yen Thuy 220kV substation, Bim Son 220kV substation, Sam Son 220kV substation
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply, transport transfer, VTTB II th and Configuration HĐKMT at the transformer station (incl includes services related)
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
3.Tender package No 4.2: Supply and transportation of secondary VTTB and Configuration of KMT at transformer stations: Dong Anh 500kV substation, Pho Noi 500kV substation, Vat Cach 220kV substation, Ba Thien 220kV substation, Phu Tho 2 220kV substation
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and transport of secondary equipment and materials, and configuration of solar power control systems at substations (including related services).
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
4.Tender package No 4.3: Supply and transportation of secondary VTTB and Configuration of KMT at transformer stations: 500kV Thuong Tin substation, 220kV Pho Cao substation, 500kV Nho Quan substation
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and transport of secondary equipment and materials, and configuration of solar power control systems at substations (including related services).
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
5.Tender package No 4.4: Supply and transportation of secondary VTTB and Configuration of MTB at Vu Thu 220kV Substation, Hai Duong 2 220kV Substation
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and transport of secondary equipment and materials, and configuration of solar power control systems at substations (including related services).
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
6.Tender package No 4.5: Supply and transportation of secondary VTTB and Configuration of MTB system at Hai Hau 220kV substation
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and transportation of secondary VTTB and configuration of KMT system (including related services)
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Phase 2 contractor selection plan Project: Installing additional 110kV horizontal capacitors on the Northern transmission grid year 2026". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Phase 2 contractor selection plan Project: Installing additional 110kV horizontal capacitors on the Northern transmission grid year 2026" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 4

You did not use the site, Click here to remain logged. Timeout: 60 second