Bidder Selection Plan

Project management consulting; Prepare bidding documents, evaluate bidding documents for construction and equipment procurement packages; Appraisal of bidding documents and LCNT results for construction and equipment procurement packages; Construction and equipment procurement; Supervision consulting; Audit consulting; Consulting on verification and approval of settlement of investment projects to build, upgrade and renovate the headquarters of the Party Committee, Fatherland Front Committee, People's Council, People's Committee, Dong Van Ward Public Administration Center to serve after arrangement and merger

  Watching      
Find: 17:13 05/11/2025
Contractor Selection Plan ID
PL2500281461-00
Publishing time
17:09 05/11/2025
Posting Status
Published
Contractor selection plan name
Project management consulting; Prepare bidding documents, evaluate bidding documents for construction and equipment procurement packages; Appraisal of bidding documents and LCNT results for construction and equipment procurement packages; Construction and equipment procurement; Supervision consulting; Audit consulting; Consulting on verification and approval of settlement of investment projects to build, upgrade and renovate the headquarters of the Party Committee, Fatherland Front Committee, People's Council, People's Committee, Dong Van Ward Public Administration Center to serve after arrangement and merger
Investment objective
Ensure spacious and synchronous facilities to meet the requirements of working, receiving citizens and running the work of local authorities.
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500057355-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
1 Years
Authority that issues the decision
Ủy ban nhân dân phường Đồng Văn
Approval date
29/10/2025
Approval ID
Số 893/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 6
1.Tender package No 01: Project management consulting
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction project management consultancy
Capital source details
Ward budget and other lawful capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
2.Package 02: Making Bidding Documents, evaluating Bid Bids of Construction Bidding Package
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bid documents, evaluate bids for construction bidding packages
Capital source details
Ward budget and other lawful capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
3.Bidding package No. 03: Appraisal of bidding documents, LCNT results of construction bidding packages
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Appraisal of bidding documents and LCNT results for construction bidding packages
Capital source details
Ward budget and other lawful capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
4.Tender package No 04: Construction and equipment procurement
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction work and equipment procurement
Capital source details
Ward budget and other lawful capital sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
5.Package No. 05: Supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision
Capital source details
Ward budget and other lawful capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
6.Package 06: Audit consulting
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Completed project audit consulting
Capital source details
Ward budget and other lawful capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project management consulting; Prepare bidding documents, evaluate bidding documents for construction and equipment procurement packages; Appraisal of bidding documents and LCNT results for construction and equipment procurement packages; Construction and equipment procurement; Supervision consulting; Audit consulting; Consulting on verification and approval of settlement of investment projects to build, upgrade and renovate the headquarters of the Party Committee, Fatherland Front Committee, People's Council, People's Committee, Dong Van Ward Public Administration Center to serve after arrangement and merger". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project management consulting; Prepare bidding documents, evaluate bidding documents for construction and equipment procurement packages; Appraisal of bidding documents and LCNT results for construction and equipment procurement packages; Construction and equipment procurement; Supervision consulting; Audit consulting; Consulting on verification and approval of settlement of investment projects to build, upgrade and renovate the headquarters of the Party Committee, Fatherland Front Committee, People's Council, People's Committee, Dong Van Ward Public Administration Center to serve after arrangement and merger" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 5

You did not use the site, Click here to remain logged. Timeout: 60 second