Bidder Selection Plan

Project: new construction additional high school Tuong Binh Hiep

  Watching      
Find: 10:56 02/04/2025
Contractor Selection Plan ID
PL2500067173-00
Publishing time
10:55 02/04/2025
Posting Status
Published
Contractor selection plan name
Project: new construction additional high school Tuong Binh Hiep
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500016799-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Authority that issues the decision
Ủy ban nhân dân tỉnh Bình Dương
Approval date
18/03/2025
Approval ID
832/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 4
1.Equipment appraisal consulting
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out price appraisal of office equipment
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location
Thủ Dầu Một City, Province Bình Dương
Implementation location (After merge)
Prequalification
No
2.Consulting on making bidding documents, evaluating bids for equipment procurement packages
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Performing contractor selection includes: Making Bidding Documents, evaluating Bid dossier ...
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Thủ Dầu Một City, Province Bình Dương
Implementation location (After merge)
Prequalification
No
3.equipment shopping
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out equipment procurement and installation
Capital source details
Provincial budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Thủ Dầu Một City, Province Bình Dương
Implementation location (After merge)
Prequalification
No
4.Equipment installation supervision consulting
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out equipment installation supervision
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Thủ Dầu Một City, Province Bình Dương
Implementation location (After merge)
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project: new construction additional high school Tuong Binh Hiep". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email