Bidder Selection Plan

Project: Ong Tai dam road (remaining section)

  Watching      
Find: 13:01 10/09/2024
Contractor Selection Plan ID
PL2400182274-01
Publishing time
09:31 10/09/2024
Posting Status
Published
Contractor selection plan name
Project: Ong Tai dam road (remaining section)
Investment objective
To connect traffic and meet the travel and goods transportation needs of people, creating landscape for the area
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400050566-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Authority that issues the decision
Uỷ ban nhân dân huyện Cái Bè
Approval date
16/08/2024
Approval ID
7212/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Total investment, total investment, Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 6
1.Package 1: Ong Tai dam road (remaining section)
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Development investment capital from the central budget to implement the national target program to build new rural areas in 2024
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Implementation location
Cái Bè District, Province Tiền Giang
Implementation location (After merge)
Prequalification
No
2.Package 2: Project management
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Project management consultancy
Capital source details
Development investment capital from the central budget to implement the national target program to build new rural areas in 2024
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Implementation location
Cái Bè District, Province Tiền Giang
Implementation location (After merge)
Prequalification
No
3.Bidding package 3: Prepare bidding documents and evaluate construction bidding documents
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents and evaluate bids
Capital source details
Development investment capital from the central budget to implement the national target program to build new rural areas in 2024
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Implementation location
Cái Bè District, Province Tiền Giang
Implementation location (After merge)
Prequalification
No
4.Package 4: Appraisal of Construction Documents and Appraisal of NTQLCQC
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting on Appraisal of Construction Documents and Appraisal of NTQL results
Capital source details
Development investment capital from the central budget to implement the national target program to build new rural areas in 2024
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Implementation location
Cái Bè District, Province Tiền Giang
Implementation location (After merge)
Prequalification
No
5.Package 5: Construction supervision
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision
Capital source details
Development investment capital from the central budget to implement the national target program to build new rural areas in 2024
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Implementation location
Cái Bè District, Province Tiền Giang
Implementation location (After merge)
Prequalification
No
6.Package 6: Insurance
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Insurance
Capital source details
Development investment capital from the central budget to implement the national target program to build new rural areas in 2024
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Implementation location
Cái Bè District, Province Tiền Giang
Implementation location (After merge)
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project: Ong Tai dam road (remaining section)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project: Ong Tai dam road (remaining section)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 17

You did not use the site, Click here to remain logged. Timeout: 60 second