Contractor Selection Plan ID
PL2200051114-00
Publishing time
10:13 21/11/2022
Posting Status
Published
Contractor selection plan name
Repair and replacement of lighting systems, lines of lighting routes in Kinh Mon town and electronic boards at the intersection of National Highway 17B Tran Hung Dao street (provincial road 389)
Investment objective
Repairing and renovating the public lighting system in the area of ​​Kinh Mon town, including: The lighting system of That Hung ward, Quang Thanh commune, An Luu, Hiep An, Long Xuyen, An Phu, and Hiep wards Son, Pham Thai, An Sinh, Duy Tan, Phu Thu, Minh Tan and the electronic board at the intersection of National Highway 17B Tran Hung Dao street (province road 389) ensure light at night to serve people's travel needs and safety. traffic, social order and security and urban beauty in Kinh Mon town
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2200025656-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
30 Date
Location
Hai Duong province
Authority that issues the decision
UBND thị xã Kinh Môn
Approval date
18/11/2022
Approval ID
1146/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 7
1.Package 02: Consulting on appraisal of bidding documents, LCNT . results
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Funding sources are not regularly assigned to the Department of Management and Training
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
2.Tender package No 06: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Funding sources are not regularly assigned to the Department of Management and Training
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
3.Bidding package No. 01: Consultancy on preparation of bidding documents, evaluation of construction and installation bids + posting notice of invitation to bid
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Funding sources are not regularly assigned to the Department of Management and Training
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
4.Tender package No 04: Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Funding sources are not regularly assigned to the Department of Management and Training
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
5.Tender package No 05: Construction audit
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Funding sources are not regularly assigned to the Department of Management and Training
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
6.Package 03: Project Management Consulting
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Funding sources are not regularly assigned to the Department of Management and Training
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
7.Tender package No 07: Construction
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Funding sources are not regularly assigned to the Department of Management and Training
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Repair and replacement of lighting systems, lines of lighting routes in Kinh Mon town and electronic boards at the intersection of National Highway 17B Tran Hung Dao street (provincial road 389)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Repair and replacement of lighting systems, lines of lighting routes in Kinh Mon town and electronic boards at the intersection of National Highway 17B Tran Hung Dao street (provincial road 389)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 11

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 7795 Projects are waiting for contractors
  • 296 Tender notices posted in the last 24 hours
  • 478 Contractor selection plan posted in the last 24 hours
  • 23745 Tender notices posted in the past month
  • 37366 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second