Bidder Selection Plan

Repairing school blocks in 2025

  Watching      
Find: 13:52 01/10/2025
Contractor Selection Plan ID
PL2500082359-01
Publishing time
13:51 01/10/2025
Posting Status
Published
Contractor selection plan name
Repairing school blocks in 2025
Investment objective
-Part damage and degradation during use to extend the life of the building and ensure the use of the project - Repair to ensure the beauty of the whole project during use - Ensuring facilities, creating favorable conditions for teaching and learning of schools in Thu Duc city
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500020718-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Authority that issues the decision
Ban quản lý dự án đầu tư xây dựng khu vực Thành phố Thủ Đức
Approval date
01/10/2025
Approval ID
39/QĐ-QLDA-32
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Decision-making agency, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 6
1.Tender package No 1: Advice on selecting contractors for construction and installation package
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out the work of making Bidding Documents, evaluating Bid Bids for construction and installation package
Capital source details
Thu Duc city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
2.Package 2: Consulting on evaluation of Bidding Documents and the results of the contractor selection of construction and installation package
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out the evaluation of Bidding Documents and the results of the selection of contractors for construction and installation package
Capital source details
Thu Duc city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
3.Tender package No 3: Construction and installation
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out the construction work
Capital source details
Thu Duc city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
4.Tender package No 4: Construction supervision
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out construction supervision
Capital source details
Thu Duc city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
5.Package number 5: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction risk insurance
Capital source details
Thu Duc city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
6.Tender package No 6: Audit consulting
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Performing the project independent audit
Capital source details
City budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Repairing school blocks in 2025". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Repairing school blocks in 2025" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 9

You did not use the site, Click here to remain logged. Timeout: 60 second