Bidder Selection Plan

Second phase contractor selection plan for Phuc Tho District Military Command Barracks Project/Hanoi Capital Command

  Watching      
Find: 13:00 12/09/2024
Contractor Selection Plan ID
PL2400196316-00
Publishing time
09:12 12/09/2024
Posting Status
Published
Contractor selection plan name
Second phase contractor selection plan for Phuc Tho District Military Command Barracks Project/Hanoi Capital Command
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300065901-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Authority that issues the decision
Bộ Quốc phòng
Approval date
11/09/2024
Approval ID
4074/QĐ-BQP
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 7
1.Tender package TV-04
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision consultancy and equipment installation
Capital source details
State budget + Hanoi city budget + Phuc Tho district budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Phúc Thọ District, Hà Nội
Implementation location (Before merge)
Ha Noi city
2.TV-05 . Tender Package
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Static compression test pile load test
Capital source details
State budget + Hanoi city budget + Phuc Tho district budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Phúc Thọ District, Hà Nội
Implementation location (Before merge)
Ha Noi city
3.Tender package TV-06
Tender/ Prequalification Notice ID
Contract execution period
330 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Audit
Capital source details
State budget + Hanoi city budget + Phuc Tho district budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Phúc Thọ District, Hà Nội
Implementation location (Before merge)
Ha Noi city
4.PTV bidding package
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance
Capital source details
State budget + Hanoi city budget + Phuc Tho district budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Phúc Thọ District, Hà Nội
Implementation location (Before merge)
Ha Noi city
5.Package XL
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction and installation of construction items; Elevator; Business tools (except medium voltage wiring system; Transformer station; 320kVA transformer station equipment and fire protection equipment)
Capital source details
State budget + Hanoi city budget + Phuc Tho district budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Phúc Thọ District, Hà Nội
Implementation location (Before merge)
Ha Noi city
6.Tender Package TB-01
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Medium voltage wiring system, transformer station; 320kVA transformer station equipment
Capital source details
State budget + Hanoi city budget + Phuc Tho district budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Phúc Thọ District, Hà Nội
Implementation location (Before merge)
Ha Noi city
7.Tender package TB-02
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Procurement of fire protection equipment
Capital source details
State budget + Hanoi city budget + Phuc Tho district budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Phúc Thọ District, Hà Nội
Implementation location (Before merge)
Ha Noi city

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Second phase contractor selection plan for Phuc Tho District Military Command Barracks Project/Hanoi Capital Command". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Second phase contractor selection plan for Phuc Tho District Military Command Barracks Project/Hanoi Capital Command" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 30

You did not use the site, Click here to remain logged. Timeout: 60 second