Bidder Selection Plan

Technical infrastructure of Nui Sam cultural park

  Watching      
Find: 11:49 20/09/2023
Contractor Selection Plan ID
PL2300170603-00
Publishing time
10:48 20/09/2023
Posting Status
Published
Contractor selection plan name
Technical infrastructure of Nui Sam cultural park
Investment objective
Investment in office park infrastructure project to transform Sam Mountain to complete the area's infrastructure to create favorable conditions for development develop tourism and connect with other regions. At the same time the completion of the project will helps residents and tourists have space to play and entertain when they come Continental Director
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300045425-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
4 Years
Authority that issues the decision
Ủy ban nhân dân thành phố Châu Đốc
Approval date
29/08/2023
Approval ID
1384
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 10
1.Tender package No 24: Construction and installation of power supply + equipment and lighting system.
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Source of Merit at the Management Board of the Temple of Mount Sam
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
October 2024
Type of contract
All in One
Prequalification
No
2.Tender package No 25: Construction items: Communication system + Sound.
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Source of Merit at the Management Board of the Temple of Mount Sam
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
October 2024
Type of contract
All in One
Prequalification
No
3.Tender package No 26: Construction and installation of items: Planting trees.
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Source of Merit at the Management Board of the Temple of Mount Sam
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January, 2025
Type of contract
All in One
Prequalification
No
4.Tender package No 22: Site leveling construction.
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Source of Merit at the Management Board of the Temple of Mount Sam
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
October, 2023
Type of contract
Fixed unit price
Prequalification
No
5.Tender package No 23: Construction and installation items: Roads, rainwater drainage systems, wastewater drainage systems, water supply.
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Source of Merit at the Management Board of the Temple of Mount Sam
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
June 2024
Type of contract
Fixed unit price
Prequalification
No
6.Bidding package No. 05: Prepare construction drawing design documents and estimates.
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Source of Merit at the Management Board of the Temple of Mount Sam
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
August 2023
Type of contract
All in One
Prequalification
No
7.Bidding package No. 13: Consulting on construction and installation supervision + equipment.
Tender/ Prequalification Notice ID
Contract execution period
990 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Source of Merit at the Management Board of the Temple of Mount Sam
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
October, 2023
Type of contract
All in One
Prequalification
No
8.Tender package No 15: Consulting on testing to control project quality.
Tender/ Prequalification Notice ID
Contract execution period
990 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Source of Merit at the Management Board of the Temple of Mount Sam
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
October, 2023
Type of contract
All in One
Prequalification
No
9.Bidding package No. 20: Audit consulting.
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Source of Merit at the Management Board of the Temple of Mount Sam
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
October 2024
Type of contract
All in One
Prequalification
No
10.Tender package No 27: Construction and installation of items: Wastewater treatment + Equipment.
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Source of Merit at the Management Board of the Temple of Mount Sam
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June 2024
Type of contract
All in One
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Technical infrastructure of Nui Sam cultural park". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Technical infrastructure of Nui Sam cultural park" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 24

You did not use the site, Click here to remain logged. Timeout: 60 second