Bidder Selection Plan

Upgrading and expanding Tran Binh Trong street, Chu Ty town

  Watching      

Warning: DauThau.info have found this plan for contractor selection violates the form of bidding as stipulated in Article 37 of Circular No. 08/2022/TT-BKHĐT, specifically: The total number of bidding packages or the total value of online bidding packages is lower than required.

-- You will be rewarded if you detect false warnings! See instructions here!

Find: 15:51 11/01/2023
Contractor Selection Plan ID
PL2300004511-00
Publishing time
15:47 11/01/2023
Posting Status
Published
Contractor selection plan name
Upgrading and expanding Tran Binh Trong street, Chu Ty town
Investment objective
In order to meet traffic demand, gradually improve infrastructure, create urban beauty and promote local socio-economic development.
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300001443-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
120 Date
Authority that issues the decision
Ủy ban nhân dân huyện Đức Cơ
Approval date
11/01/2023
Approval ID
117/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 3
1.Cost of Proposal Preparation and Proposal evaluation
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Balanced source according to the criteria that the province decentralizes for the district to decide on investment
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
2.Construction supervision consultant
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Balanced source according to the criteria that the province decentralizes for the district to decide on investment
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
3.Construction and installation works
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Balanced source according to the criteria that the province decentralizes for the district to decide on investment
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Upgrading and expanding Tran Binh Trong street, Chu Ty town". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Upgrading and expanding Tran Binh Trong street, Chu Ty town" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 22

You did not use the site, Click here to remain logged. Timeout: 60 second