Status
Complete opening of financial documents
Bidding package name
Package 4: Construction supervision consultancy
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Contractor selection plan Project: Repairing road surface, completing traffic safety system, section Km94+200 - Km102+500, National Highway 30, Dong Thap province
Contract execution period
180 day
Contractor selection methods
Competitive Bidding
Award date
11:30 25/12/2023
Bid opening completion time
11:31 25/12/2023
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)
Estimated price
647.700.000 VND