Status
Tender opening completed
Bidding package name
Tender package No 01: The whole Construction part
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Plan for selecting construction contractors: building new houses and auxiliary works
Contract execution period
6 day
Contractor selection methods
Competitive Offer
Award date
08:00 12/03/2025
Bid opening completion time
08:37 12/03/2025
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)