Bidder Selection Plan
additional contractor selection plan
Contractor selection plan ID
20180836557-00
Publication date
16:46 16/08/2018
Publication status
Actual notification
Contractor selection plan name
additional contractor selection plan
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
List of Bid:
Number of packages: 8
1. Prepare bidding documents and evaluate bids for construction bidding packages
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2018
2. Prepare bidding documents and evaluate bids for construction supervision consultancy bidding packages
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2018
3. Appraisal of bidding documents, LCNT results of construction bidding packages
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2018
4. Appraisal of bidding documents, LCNT results of construction supervision consultancy bidding package
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2018
Tender/ Prequalification Notice ID
Contract Period
24 months
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
6. Supervision of construction works
Tender/ Prequalification Notice ID
Contract Period
24 months
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
7. Static load test of piles (03 piles)
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2018
Tender/ Prequalification Notice ID
Contract Period
24 months
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "additional contractor selection plan". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email