Bidder Selection Plan

Contractor selection plan for phase 3 - Van Dien 220kV Transformer Station Project and connection

  Watching      
Find: 10:28 23/02/2024
Contractor Selection Plan ID
PL2400021728-00
Publishing time
10:28 23/02/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan for phase 3 - Van Dien 220kV Transformer Station Project and connection
Investment objective
- Meet the power demand for the 110 kV power grid in the south of the city. Hanoi, medium voltage loads in Thanh Tri district and neighboring areas. - Create strong connections between areas in the power system, increasing the safe and stable operation of the national power system. - Increase power supply stability, reduce capacity loss, electricity loss in the system, improve EVN's production and business efficiency.
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400006452-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
5 Years
Authority that issues the decision
TỔNG CÔNG TY TRUYỀN TẢI ĐIỆN QUỐC GIA
Approval date
22/02/2024
Approval ID
35/QĐ-HĐTV
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Filter name, Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 16
1.Tender package No 7: Supply and transportation of Transformer
Tender/ Prequalification Notice ID
Contract execution period
7 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Goods
Regulatory compliance
CPTPP/EVFTA/UKVFTA
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and delivery of transformers
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
April 2024
Type of contract
All in One
Implementation location
Prequalification
No
2.Tender package No 8: Supply and transportation of first-class VTTB (Including lightning protection and cable column valves)
Tender/ Prequalification Notice ID
Contract execution period
8 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Goods
Regulatory compliance
CPTPP/EVFTA/UKVFTA
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and transportation of first-class VTTB (Including lightning protection and cable connection column valves)
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2024
Type of contract
All in One
Implementation location
Prequalification
No
3.Tender package No 9: Supply and transport of secondary VTTB and information VTTB
Tender/ Prequalification Notice ID
Contract execution period
6 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and transport of secondary VTTB and informational VTTB
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
May 2024
Type of contract
All in One
Implementation location
Prequalification
No
4.Bidding package No. 10: Providing equipment and software for computer control systems
Tender/ Prequalification Notice ID
Contract execution period
6 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Providing equipment and software of computer control system
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
June 2024
Type of contract
All in One
Implementation location
Prequalification
No
5.Tender package No 11: Supply, transport, install, connect, and test underground cables for the Van Dien - Thuong Tin 1 line section (including cable temperature monitor)
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Goods
Regulatory compliance
CPTPP/EVFTA/UKVFTA
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply, transport, install, connect, and test underground cables for the Van Dien - Thuong Tin 1 section (including cable temperature monitor)
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2024
Type of contract
Package and Fixed Price
Implementation location
Prequalification
No
6.Tender package No 12: Supply, transport, installation, connection, and testing of underground cables for the Van Dien - Thuong Tin 2 line section
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Goods
Regulatory compliance
CPTPP/EVFTA/UKVFTA
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply, transport, installation, connection, and testing of underground cables for the Van Dien - Thuong Tin 2 line section
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2024
Type of contract
Package and Fixed Price
Implementation location
Prequalification
No
7.Tender package No 13: Supply, transport, installation, connection, and testing of underground cables for the Van Dien - Ha Dong 1 line section
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Goods
Regulatory compliance
CPTPP/EVFTA/UKVFTA
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply, transport, installation, connection, and testing of underground cables for the Van Dien - Ha Dong 1 line section
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2024
Type of contract
Package and Fixed Price
Implementation location
Prequalification
No
8.Tender package No 14: Supply, transport, installation, connection, and testing of underground cables for the Van Dien - Ha Dong 2 line section
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Goods
Regulatory compliance
CPTPP/EVFTA/UKVFTA
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply, transport, install, connect, and test underground cables for the Van Dien - Ha Dong 2 line section
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2024
Type of contract
Package and Fixed Price
Implementation location
Prequalification
No
9.Tender package No 15: Construction of underground cable ditches, cable connection tunnels, column foundations, supply and erection of steel columns, materials for connecting 220kV overhead lines
Tender/ Prequalification Notice ID
Contract execution period
11 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of underground cable trenches, cable connection tunnels, column foundations, supply and erection of steel columns, materials for connecting 220kV overhead lines
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2024
Type of contract
Fixed unit price
Implementation location
Prequalification
No
10.Tender package No 16: Construction and installation of transformer stations (including implementation of fire protection, law enforcement and SCADA works)
Tender/ Prequalification Notice ID
Contract execution period
15 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction and installation of transformer stations (including implementation of fire protection, law enforcement and SCADA works)
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2024
Type of contract
Fixed unit price
Implementation location
Prequalification
No
11.Tender package No 17: Providing installation services, connecting and integrating protection control systems; Transformer installation and calibration experiments
Tender/ Prequalification Notice ID
Contract execution period
4 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Providing installation services, connecting and integrating protection control systems; Transformer installation and calibration experiments
Capital source details
Capital EVNNPT
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
September 2024
Type of contract
All in One
Implementation location
Prequalification
No
12.Tender package No 18: Providing consulting services for construction supervision and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
15 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Providing consulting services for construction supervision and equipment installation
Capital source details
EVNNPT
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2024
Type of contract
All in One
Implementation location
Prequalification
No
13.Tender package No 19: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
39 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance for the project
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2024
Type of contract
By percentage
Implementation location
Prequalification
No
14.Package 20: Audit of completed project settlement reports
Tender/ Prequalification Notice ID
Contract execution period
2 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Audit of completed project settlement reports
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
July 2025
Type of contract
All in One
Implementation location
Prequalification
No
15.Tender package No 21: Survey, prepare plans, construction estimates and supervise bomb, mine and explosive material clearance
Tender/ Prequalification Notice ID
Contract execution period
3 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Survey, make plans, estimate construction and supervise construction of bomb, mine and explosive material clearance
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
February 2024
Type of contract
All in One
Implementation location
Prequalification
No
16.Tender package No 22: Construction of bomb, mine, and explosive material clearance
Tender/ Prequalification Notice ID
Contract execution period
1 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction to clear bombs, mines and explosives
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
April 2024
Type of contract
All in One
Implementation location
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for phase 3 - Van Dien 220kV Transformer Station Project and connection". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for phase 3 - Van Dien 220kV Transformer Station Project and connection" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 65

You did not use the site, Click here to remain logged. Timeout: 60 second