Bidder Selection Plan
Cremation facility for Khmer ethnic people
Contractor selection plan ID
20210119373-00
Publication date
16:08 13/01/2021
Publication status
Actual notification
Contractor selection plan name
Cremation facility for Khmer ethnic people
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20210119330-00
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Approval Documents
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files. To download, please Login or Register
List of Bid:
Number of packages: 21
1. Package 1: Design construction drawings, cost estimates
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
December 2020
2. Package 2: Verification of construction drawing design, cost estimate
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
3. Package 3: Prepare Bidding Documents and analyze and evaluate bids for construction and installation bidding package No. 1
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
4. Package 4: Evaluation of bidding documents and appraisal of contractor selection results for construction and installation bidding package No. 1
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
5. Package 5: Preparation of Bidding Documents and Analysis and Evaluation of Bid Documents for Consulting Service Tender package No 7
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
6. Package 6: Evaluation of bidding documents and evaluation of contractor selection results for consulting service package No. 7
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
7. Package 7: Supervision of construction of items (except for items in construction and installation bidding packages No. 2 and No. 3)
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
8. Package 8: Construction supervision of construction and installation bidding package No. 2
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2021
9. Tender package No 9: Construction supervision of construction and installation bidding package No. 3
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2021
10. Package 10: Supervision of equipment installation and procurement package of goods and equipment No. 1
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
11. Package 11: Supervision of equipment installation and procurement of goods and equipment No. 2 and No. 3
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
12. Package 12: Static test compression of BTC cọc piles
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
13. Package 13: Appraisal of equipment
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2021
14. Package 14: Checking the acceptance of construction works
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
15. Package 1: Construction insurance
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2021
16. Package 1: Office equipment
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
17. Package 2: Specialized vehicle
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
18. Package #3: Backup generator 75kVA
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
19. Package 1: Construction of work items and installation of equipment (except for items in construction and installation bidding packages No. 2 and No. 3)
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
Contract Type
According to fixed unit price
20. Package 2: Substation 3x25kVA
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2021
21. Package 3: Fire protection system, lightning protection
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Targeted additional central capital (source of funding for the cause of environmental protection)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2021
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Cremation facility for Khmer ethnic people". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email