Bidder Selection Plan

Relocate the lane to Gate B Tan Cang Cat Lai port

  Watching      
Find: 13:55 14/04/2025
Contractor Selection Plan ID
PL2500079243-00
Publishing time
13:54 14/04/2025
Posting Status
Published
Contractor selection plan name
Relocate the lane to Gate B Tan Cang Cat Lai port
Investment objective
Relocate the lane to Gate B Tan Cang Cat Lai port to achieve the following goal: - Increasing labor productivity, transferring computer staff to take better working environment positions instead of self -service kiosk system. - Increasing delivery productivity, reducing delivery time. 3 - Increase the accuracy in delivery. - Ensuring seaport security, good management of vehicles and people in and out of the gate. - Storing images of container faces for delivery and receipt work.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500019567-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Authority that issues the decision
Công ty TNHH MTV Tổng công ty Tân cảng Sài Gòn
Approval date
11/04/2025
Approval ID
1472/QĐ-TCg
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 2
1.Package 1: Construction, installation and supply and installation of equipment - works: Modifying lanes to Gate B Cat Lai Port Port
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of pile foundation gate (including static pile test), frame system structure, steel column, tole roof, front yard and backyard are renovated from so asphalt concrete into reinforced concrete floor, drainage ditch and temporary fence ... Supply and install equipment according to the approved design documents
Capital source details
Equity (accounting of fixed assets of TCT)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
April, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Ho Chi Minh city
2.Package 2: Supervision of construction and installation, supply and installation of equipment - works: Modifying lanes to Gate B Tan Cang Cat Lai port
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Monitoring in the process of construction, installation and supply, installation of equipment and other jobs of the package No. 1
Capital source details
Equity (accounting of fixed assets of TCT)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
April, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Ho Chi Minh city

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Relocate the lane to Gate B Tan Cang Cat Lai port". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Relocate the lane to Gate B Tan Cang Cat Lai port" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 9

You did not use the site, Click here to remain logged. Timeout: 60 second