Data analysis results of DauThau.info software for bid solicitors Hydropower Project Management Board No1 as follows:
- Has relationships with 1 project owners.
- Has relationships with 20 contractor.
- Announced 1 investment development project, of which 0 projects have not yet announced the prequalification documents.
- Announced 12 contractor selection plans with a total of 35 bidding packages, of which 9 prequalification documents have not found the investment project.
- Has invited bids for 45 packages (with 46 tender notices), and conducted prequalification for 2 packages.
- There are 0 bidding packages with content that needs clarification.
- Announced the results of 20 package, and canceled bids for 0 packages (among the packages mentioned above).
- There are 9 packages with results that do not have tender notice or prequalification notice.
- There are 0 packages with results that do not have Contractor selection plan.
- There are 26 packages that have not fully posted the contractor selection results. Of these 25 bidding packages have no tender notices found.
- On average, the number of contractors participating in each package is: 1.67 contractors.
- Breakdown by bidding field: Goods 63.04%, Construction 13.04%, Consultancy 21.74%, Non-consultancy 2.17%, Mixed 0%, Other fields 0%.
- The total value according to the packages with valid contractor selection results is: 69,073,384,576 VND, of which the total winning bid value is: 62,129,930,063 VND.
- The savings rate is: 10.05%.
Data analysis results of DauThau.info software for bid solicitors Hydropower Project Management Board No1 as follows:
- Has relationships with 20 contractor.
- The average number of contractors participating in each bidding package is: 1.67 contractors.
- Proportion of bidding fields: Goods 63.04%, Construction 13.04%, Consulting 21.74%, Non-consulting 2.17%, Mixed 0%, Other 0%.
- The total value according to the bidding package with valid IMP is: 69,073,384,576 VND, in which the total winning value is: 62,129,930,063 VND.
- The savings rate is: 10.05%.
This Bid solicitor is also an investor. The analysis results of data for the investor Hydropower Project Management Board No1 are as follows:
- Is the investor of 1 development investment projects.
- Is the investor of 3 contractor selection plans, of which 3 were self-published, and 0 were published by other entities.
- Is the investor of 17 Tender Notices, of which 11 were self-invited, and 6 were invited by other entities.
| Evaluation criteria | Evaluation score |
|---|---|
| Experience | ??? |
| Financial capacity | ??? |
| Transparency of the investor/bidder | ??? |
| Bidding efficiency | ??? |
The Bid solicitor Hydropower Project Management Board No1 has posted the results of the bidding package Package 07 (BM-03): Construction of clearing mines and explosives in the construction area of Se San 4 Solar Power Plant Project of the investor Hydropower Project Management Board No1.
02/01/2019 09:46
The Bid solicitor Hydropower Project Management Board No1 has posted the results of the bidding package Package 04 (TV-03): Consulting on surveying and mapping cadastral maps for preparation of documents and procedures for land recovery, land allocation, land use purpose change for compensation and support work clearance of the investor Hydropower Project Management Board No1.
25/10/2018 13:53
The Bid solicitor Hydropower Project Management Board No1 has posted the results of the bidding package Package No. 09 (XL-01): Construction, renovation and repair of the office and housing of the Project Management Board at Se San 4 project of the investor Hydropower Project Management Board No1.
25/10/2018 13:16
The Bid solicitor Hydropower Project Management Board No1 has posted the results of the bidding package Package 2 (TV-01): Consulting on evaluating prequalification documents, EPC bids and assisting in EPC contract negotiation of the investor Hydropower Project Management Board No1.
12/10/2018 15:17
Investor Hydropower Project Management Board No1 has posted an investment and development project Sesan 4 . solar power plant.
20/08/2018 09:09
The Bid solicitor Hydropower Project Management Board No1 has posted the results of the bidding package Package 2: Procurement of desktop computers, A3 printers, A4 printers under the cost of Hydropower Project Management Board 1 in 2018 of the investor Hydropower Project Management Board No1.
13/08/2018 14:44
Bid solicitor Hydropower Project Management Board No1 has posted Tender Notice Package 2: Procurement of desktop computers, A3 printers, A4 printers under the cost of Hydropower Project Management Board 1 in 2018 of the investor Hydropower Project Management Board No1 with the form Competitive offers- No prequalification - Only domestic contractors.
19/07/2018 08:49
The Bid solicitor Hydropower Project Management Board No1 has posted the results of the bidding package Consulting and verifying feasibility study report on investment and construction of the expanded Ialy hydroelectric power plant project of the investor Hydropower Project Management Board No1.
- Winning bidder: Công ty Cổ phần Tư vấn Xây dựng Điện 2
14/06/2018 11:21
The Bid solicitor Hydropower Project Management Board No1 has posted the request Procurement of desktop computers, A3 printers, A4 printers at the expense of Hydropower Project Management Board 1 in 2018 of the investor Hydropower Project Management Board No1 with 1 bidding package.
04/06/2018 15:29
The Bid solicitor Hydropower Project Management Board No1 has posted the request Consulting and verifying feasibility study report for construction investment of Se San 4 solar power plant project of the investor Hydropower Project Management Board No1 with 1 bidding package.
04/05/2018 14:36
The data sheet has been partially hidden, to see the full information please Login or Register
Hydropower Project Management Board No1 publishes the plan Contractor selection plan for package No. 01 (HH-EPC): Design, supply of goods, construction and installation (EPC) with 1 bidding package .
04/03/2019 14:56
Hydropower Project Management Board No1 announced the results of the bid package Package 07 (BM-03): Construction of clearing mines and explosives in the construction area of Se San 4 Solar Power Plant Project .
- Winning bidder: TỔNG CÔNG TY XÂY DỰNG TRƯỜNG SƠN
02/01/2019 09:46
Hydropower Project Management Board No1 announced the results of the bid package Package 04 (TV-03): Consulting on surveying and mapping cadastral maps for preparation of documents and procedures for land recovery, land allocation, land use purpose change for compensation and support work clearance .
- Winning bidder: Công ty Cổ phần Đo đạc và Bản đồ Viễn Thám
25/10/2018 13:53
Hydropower Project Management Board No1 announced the results of the bid package Package No. 09 (XL-01): Construction, renovation and repair of the office and housing of the Project Management Board at Se San 4 project .
- Winning bidder: CÔNG TY TNHH TƯ VẤN ĐẦU TƯ VÀ XÂY DỰNG YÊN HƯNG
25/10/2018 13:16
Hydropower Project Management Board No1 announced the results of the bid package Package 2 (TV-01): Consulting on evaluating prequalification documents, EPC bids and assisting in EPC contract negotiation .
- Winning bidder: CÔNG TY CỔ PHẦN TƯ VẤN XÂY DỰNG ĐIỆN 1
12/10/2018 15:17
Hydropower Project Management Board No1 announced the results of the bidding package Package 2 (TV-01): Consulting on evaluating prequalification documents, EPC bids and assisting in EPC contract negotiation with 2 participating contractors .
05/10/2018 09:18
Hydropower Project Management Board No1 publishes Tender Notice Package 2 (TV-01): Consulting on evaluating prequalification documents, EPC bids and assisting in EPC contract negotiation in the form National competitive bidding .
07/09/2018 15:26
Hydropower Project Management Board No1 publishes the plan Plan to select contractor for Sesan 4 solar power plant project (49Mw) with 9 bidding package .
20/08/2018 14:48
The data sheet has been partially hidden, to see the full information please Login or Register
The Bid solicitor Hydropower Project Management Board No1 has posted the results of the bidding package Package 07 (BM-03): Construction of clearing mines and explosives in the construction area of Se San 4 Solar Power Plant Project of the investor Hydropower Project Management Board No1.
02/01/2019 09:46
The Bid solicitor Hydropower Project Management Board No1 has posted the results of the bidding package Package 04 (TV-03): Consulting on surveying and mapping cadastral maps for preparation of documents and procedures for land recovery, land allocation, land use purpose change for compensation and support work clearance of the investor Hydropower Project Management Board No1.
25/10/2018 13:53
The Bid solicitor Hydropower Project Management Board No1 has posted the results of the bidding package Package No. 09 (XL-01): Construction, renovation and repair of the office and housing of the Project Management Board at Se San 4 project of the investor Hydropower Project Management Board No1.
25/10/2018 13:16
The Bid solicitor Hydropower Project Management Board No1 has posted the results of the bidding package Package 2 (TV-01): Consulting on evaluating prequalification documents, EPC bids and assisting in EPC contract negotiation of the investor Hydropower Project Management Board No1.
12/10/2018 15:17
Investor Hydropower Project Management Board No1 has posted an investment and development project Sesan 4 . solar power plant.
20/08/2018 09:09
The Bid solicitor Hydropower Project Management Board No1 has posted the results of the bidding package Package 2: Procurement of desktop computers, A3 printers, A4 printers under the cost of Hydropower Project Management Board 1 in 2018 of the investor Hydropower Project Management Board No1.
13/08/2018 14:44
Bid solicitor Hydropower Project Management Board No1 has posted Tender Notice Package 2: Procurement of desktop computers, A3 printers, A4 printers under the cost of Hydropower Project Management Board 1 in 2018 of the investor Hydropower Project Management Board No1 with the form Competitive offers- No prequalification - Only domestic contractors.
19/07/2018 08:49
The Bid solicitor Hydropower Project Management Board No1 has posted the results of the bidding package Consulting and verifying feasibility study report on investment and construction of the expanded Ialy hydroelectric power plant project of the investor Hydropower Project Management Board No1.
- Winning bidder: Công ty Cổ phần Tư vấn Xây dựng Điện 2
14/06/2018 11:21
The Bid solicitor Hydropower Project Management Board No1 has posted the request Procurement of desktop computers, A3 printers, A4 printers at the expense of Hydropower Project Management Board 1 in 2018 of the investor Hydropower Project Management Board No1 with 1 bidding package.
04/06/2018 15:29
The Bid solicitor Hydropower Project Management Board No1 has posted the request Consulting and verifying feasibility study report for construction investment of Se San 4 solar power plant project of the investor Hydropower Project Management Board No1 with 1 bidding package.
04/05/2018 14:36
The data sheet has been partially hidden, to see the full information please Login or Register
To receive this bid solicitor's earliest contractor selection plan by email, please create register for the VIP2 package.
Summary: The bid solicitor’s Hydropower Project Management Board No1 has posted 12 of the contractor selection plan, which contains 35 of the bidding package. The data sheet has been partially hidden, to see the full information please Login or Register
Summary: The Bid solicitor Hydropower Project Management Board No1 posted 2 Prequalifying Invitation Notice. The data sheet has been partially hidden, to see the full information please Login or Register
To receive the earliest Tender Notice of this Bid solicitor via email, please register for the VIP1 package.
Summary: The Bid solicitor Hydropower Project Management Board No1 has posted 46 Tender Notices in 45 bidding packages. Among these, 5 Tender Notices were self-invited, and 41 Tender Notices were invited on behalf of other investors. The data sheet has been partially hidden, to see the full information please Login or Register
Summary: The Bid solicitor Hydropower Project Management Board No1 has posted 20 contractor selection result in which:The data sheet has been partially hidden, to see the full information please Login or Register
- Published the results of the 20 package, canceled the bid 0 package (among the bidding packages above).
- There are 9 packages with no results found tender notice, Prequalifying Invitation Notice.
Summary: The Bid solicitor Hydropower Project Management Board No1 has a relationship with 20 contractors. The data sheet has been partially hidden, to see the full information please Login or Register
Summary: The procuring entity Hydropower Project Management Board No1 has a relationship with 3 investors. The data sheet has been partially hidden, to see the full information please Login or Register
If you are still not our member, please sign up.You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!
Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.
Detailed instructions on how to deposit money and redeem points on DauThau.info
When does contract negotiation fail?
[VIDEO] Guide for bid solicitors to Extend the Bid Submission Deadline
[VIDEO] Guide to Evaluating Bid Documents on the New National Bidding Network System
[VIDEO] Guide to Posting Tender Notices for PPP Projects
[VIDEO] Guide to Posting Prequalification Notices for PPP Projects
[VIDEO] Guide to Responding to Clarification Requests for e-HSMST (E-Prequalification Invitation Documents) of PPP Projects on the New National Bidding Network System
[VIDEO] Guide to Uploading the Shortlist for PPP Projects