* Flood shelter:
- Scale: New construction of a 1-storey block, 6.8 m high. Total construction area 213m2.
- Structural solution: The building uses a reinforced concrete (BTCT) single foundation system with durability grade B20 (M250). The body uses a system of frames, beams, and B20 reinforced concrete floors to support the main force. Using AI grade D6, D8 reinforcement (Rs=2300kG/cm2); steel D>=10 grade AII (Ra=2800kG/cm2);
- Finishing solution: KT 600x600 granite tile floor. The inner and outer walls of the house are built of bricks with a thickness of 15÷20 cm, painted in 3 countries. Natural granite paving steps. The roof: 0.42 mm thick corrugated iron and tile, KT40x80x1.2mm galvanized box steel purlins, plastic coated steel storm protection. Doors, windows, glass walls use 2mm thick aluminum frame doors, 8mm thick tempered white glass. Toilet: Non-slip ceramic tile floor KT300x300; 2.5m high KT 300x600 ceramic tile wall, 0.3mm thick cold corrugated iron ceiling, 30x60x1.2mm galvanized steel box purlin.
- Power supply solution: Power supply is available. connect from the existing power supply system in the area to the main switchboard by CXV/XLPE cable 2x6mm2. Power supply to electrical equipment by Cu/PVC wire 2x2,5mm2, 2x1.5mm2 threaded in protective plastic pipes going underground in walls and ceilings.
- Solution for water supply and drainage: Water source is provided taken from the bore well leading to 02 water tanks located on the roof with a capacity of 1.5m3 by PPR pipe with diameter D32; From the tank, water is supplied to the use areas on the floors by PPR pipes (32÷20)mm in diameter. Draining water for washing toilets using Upvc plastic pipes.
* Leveling, ground embankment, concrete yard:
- Leveling area 447m2, level 3 , the average embankment height is 0.9m, the land is expected to be taken in the area about 6km from the work.
- Total area 97 m2, 10cm thick M100 concrete.
- Embankment for retaining rock and rock M100, length 65m; segment A-B 55cm high; section B-C average embankment height (average) 55cm to 1.8m; section C-D average height 1.8m to 0.95m; section D-E average height from 1.15m to 4m; section E-F TB 4m to 1.2m; the F-G segment is 1.2m high;
Bidding documents on the Public Procurement System may be infected with viruses or errors, some files require computers using Windows operating systems and need to install Client Agent software (Linux and MacOS operating systems cannot install Client software) to be able to download. Using DauThau.info software, you can check all the above problems as well as preview the total size of the bidding documents to prevent missing files from downloading.
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register
Costs related to contractors when conducting bidding on public procurement (Article 12 of Decree 24/2024/ND-CP)
If you are still not our member, please sign up.You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!
Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.
When does contract negotiation fail?
[VIDEO] Guide for bid solicitors to Extend the Bid Submission Deadline
[VIDEO] Guide to Evaluating Bid Documents on the New National Bidding Network System
[VIDEO] Guide to Posting Tender Notices for PPP Projects
[VIDEO] Guide to Posting Prequalification Notices for PPP Projects
[VIDEO] Guide to Responding to Clarification Requests for e-HSMST (E-Prequalification Invitation Documents) of PPP Projects on the New National Bidding Network System
[VIDEO] Guide to Uploading the Shortlist for PPP Projects
[VIDEO] Guide for Bid Solicitors to Extend the Prequalification Document Submission Date for PPP Projects
Are you sure you want to download cargo data? If yes, please wait for the system for a moment, so that the system can download the data to your device!
No goods data
Similar goods purchased by Bid solicitor TLD CONSULTANT INVESTMENT AND CONSTRUCTION JOINT-STOCK COMPANY:
No similar goods purchased by the soliciting party were found.
Similar goods purchased by other Bid solicitors excluding TLD CONSULTANT INVESTMENT AND CONSTRUCTION JOINT-STOCK COMPANY:
No similar goods have been found that other Bid solicitors have purchased.
Similar goods for which the bidding results of the Ministry of Health have been announced:
No similar goods have been found in the bidding results of the Ministry of Health.