Contractor selection plan (phase 2 - overall) Hoa Binh Power Plant Expansion Project

  Watching      
This Contractors Selection Plan data is found on both the old and new Public Procurement systems. The data you are viewing is updated from the new Public Procurement system
Find: 10:29 11/05/2023
Contractor Selection Plan ID
20191085960-01
Publishing time
10:14 11/05/2023
Posting Status
Published
Contractor selection plan name
Contractor selection plan (phase 2 - overall) Hoa Binh Power Plant Expansion Project
Project management forms
Another form
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20191063627-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group A
Authority that issues the decision
HĐTV EVN
Approval date
09/05/2023
Approval ID
58/QĐ-HĐTV
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Investor, Decision-making agency, Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Lowest bid price, Publication date, Bidding package information (View changes)

- Change: Investor, Lowest bid price, Approval date, Publication date, Bidding package information (View changes)

- Change: Investor, Total investment, Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Investor, Total investment, Lowest bid price, Decision-making agency, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 10
1.Tender package No 14TV-HB: Consulting to convert investment capital to construction works after completion, acceptance, handover and put into use
Tender/ Prequalification Notice ID
Contract execution period
6 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's equity, Commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
August, 2025
Type of contract
All in One
Prequalification
No
Implementation location
2.Tender package No 13TV-HB: Project audit consulting
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's equity, Commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
April, 2025
Type of contract
All in One
Prequalification
No
Implementation location
3.Tender package No 3TB-HB: Supply and installation of elevators for the factory
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's equity, Commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
March, 2024
Type of contract
All in One
Prequalification
No
Implementation location
4.Tender package No 6PTV-HB: Checking welding seams
Tender/ Prequalification Notice ID
Contract execution period
22 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's equity, Commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2023
Type of contract
Fixed unit price
Prequalification
No
Implementation location
5.Tender package No 4PTV-HB: Editing archives of Hoa Binh Hydropower Plant Extension Project
Tender/ Prequalification Notice ID
Contract execution period
6 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's equity, Commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
May, 2025
Type of contract
Fixed unit price
Prequalification
No
Implementation location
6.Tender package No 5PTV-HB: Measuring and testing samples of the power metering system
Tender/ Prequalification Notice ID
Contract execution period
6 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's equity, Commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
August 2024
Type of contract
All in One
Prequalification
No
Implementation location
7.Tender package No 1PTV-HB: Transport of electromechanical equipment, transformers and 500kV GIS distribution station
Tender/ Prequalification Notice ID
Contract execution period
28 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's equity, Commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
October, 2022
Type of contract
Fixed unit price
Prequalification
No
Implementation location
8.Tender package No 3HH-HB: Supply of materials and equipment, construction and installation of items to renovate 220kV transmission lines and install 500kV lines connecting from Hoa Binh hydropower plant to the national power system.
Tender/ Prequalification Notice ID
Contract execution period
23 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Uncategoried
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's equity, Commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
June, 2023
Type of contract
Package and Fixed Price
Prequalification
No
Implementation location
9.Tender package No 7PTV-HB: Inspection and registration of pressure equipment and small cranes in the factory
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's equity, Commercial loan
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
April 2024
Type of contract
All in One
Prequalification
No
Implementation location
10.Tender package No 12TV-HB: Landscape architectural design consultancy for Hoa Binh hydropower plant expansion
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's equity, Commercial loan
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
October, 2023
Type of contract
All in One
Prequalification
No
Implementation location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan (phase 2 - overall) Hoa Binh Power Plant Expansion Project". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan (phase 2 - overall) Hoa Binh Power Plant Expansion Project" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 21

You did not use the site, Click here to remain logged. Timeout: 60 second