Bidder Selection Plan

Plan for selecting contractors for the Naval Region 1 Training Battalion project

  Watching      
Find: 08:38 10/06/2024
Contractor Selection Plan ID
PL2300158650-01
Publishing time
08:37 10/06/2024
Posting Status
Published
Contractor selection plan name
Plan for selecting contractors for the Naval Region 1 Training Battalion project
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300042545-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Authority that issues the decision
Bộ Quốc phòng
Approval date
05/06/2024
Approval ID
2325/QĐ-BQP
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Total investment, Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 13
1.Bidding package No. 05: Consulting on TKBVTC-DT
Tender/ Prequalification Notice ID
Contract execution period
70 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province
2.Package 06: Verification of TKBVTC-DT
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province
3.Bidding Package 07: Bidding consultancy, Bid evaluation
Tender/ Prequalification Notice ID
Contract execution period
350 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province
4.Tender package No 8
Tender/ Prequalification Notice ID
Contract execution period
450 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting on construction supervision + installation of equipment and tools
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province
5.Tender package No 9
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting for static compression of BTC piles
Capital source details
Government budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province
6.Tender package No 10
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of a dining room + common activities; housing c2 (S4); housing c3 (S5); 02 water heaters c2 and c3; logistics and general warehouses; 02 hot water heating systems; 01 dining room elevator
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province
7.Tender package No 11
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of battalion command house (S1); housing c1 (S3); housing c4 (S6); 02 water heaters c1 and c4; guard house, on duty; motorbike garage; main gate, guard post; parade gathering yard; flagpole; command board; 120m3 water tank; fence; 02 hot water heating systems
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province
8.Tender package No 12
Tender/ Prequalification Notice ID
Contract execution period
390 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Internal road yard; external network drainage; wastewater treatment; power supply outside the house; communication system; 320KVA substation, RMU cabinet...
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province
9.Tender package No 13
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Domestic water supply + fire prevention; Fire protection + SH water pump; Fire protection systems of construction items
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province
10.Tender package No 14
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Anti termite works
Capital source details
Government budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province
11.Tender package No 15
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
provide business tools
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province
12.BIDDING PACKAGE NO.16
Tender/ Prequalification Notice ID
Contract execution period
450 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Audit
Capital source details
Government budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province
13.BIDDING PACKAGE NO. 17
Tender/ Prequalification Notice ID
Contract execution period
450 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Insurance
Capital source details
Government budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hạ Long City, Quảng Ninh
Implementation location (Before merge)
Quang Ninh province

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Plan for selecting contractors for the Naval Region 1 Training Battalion project". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Plan for selecting contractors for the Naval Region 1 Training Battalion project" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 29

You did not use the site, Click here to remain logged. Timeout: 60 second